The serial number (1) is on a plate, on the right side on the
auxiliary single-sheave boom nose (Figure 6-182).
Installing/Removing Auxiliary Single-Sheave
Boom Nose
Installing Auxiliary Single-Sheave Boom Nose
1. Remove the retaining clips from the pins (2) and remove
the pins from the attachment lugs (Figure 6-182).
2. Use an auxiliary crane attached to the lifting eye (3) on
the auxiliary boom nose and lift it to the front of the main
boom head.
3. Align the auxiliary single-sheave boom nose so that the
attachment lugs (1, Figure 6-183) line up to the boom
nose attachment lugs (2).
4. Secure the auxiliary single-sheave boom nose to the
main boom nose using pins (3).
5. Secure the pins (3) with retaining clips (4).
6. Depending on the application, bring the auxiliary single-
sheave boom nose into transport position or working
position.
DANGER
Crushing Hazard!
During installation and removal, always use the proper
equipment with sufficient load bearing capacities.
FIGURE 6-183
8994-1
1
2
3
5
1
2
3
3
4
4
Transport Position
Working Position
Intermediate Position
5
6
7
8
9
9