EasyManuals Logo

Manitowoc Grove TMS9000-2 Series User Manual

Manitowoc Grove TMS9000-2 Series
430 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #348 background imageLoading...
Page #348 background image
SET-UP AND INSTALLATION TMS9000-2 OPERATOR MANUAL
6-12
Published 02-21-2019, Control # 611-05
RIGGING WORK FOR CRANE OPERATION
WITH THE MAIN BOOM
If the truck crane on the site has already been rigged,
proceed according to: Checks before operating the crane,
page 4-49.
NOTE: This procedure is not complete. There are
accompanying operating instructions which are
indicated by cross-references.
Observe the warnings and safety instructions
there.
Rigging
1. Check that the parking brake is applied – if necessary,
apply the parking brake.
2. If the main boom is resting on a trailer:
- Switch off the boom floating position.
- Switch off the swing gear freewheel.
NOTE: The following points only apply to rigging in Free on
wheels working position. Continue the procedure at
point 7 when rigging the truck crane on outriggers.
3. For the free on wheels working position:
NOTE: Working on free on wheels position is not allowed,
unless optional rubber charts are specified, and
these are only for directly over the rear of the
machine.
- Check that the tire pressure is correctly set.
- Check that the ground can support the maximum
axle loads.
4. Align the truck crane horizontally with the level
adjustment system.
5. On the outriggers:
- Deflate suspension before extending outriggers.
- Extend all outrigger beams as far as possible.
- Move all outrigger pads into the working position.
- Extend all outrigger cylinders far enough so that the
outrigger pads are just above the ground.
NOTE: The following points only apply when rigging the
truck crane on outriggers. To continue rigging in the
Free on wheels working position, continue the
procedure at point 11.
6. Check that the ground will support the maximum
occurring outrigger pressures.
7. Deflate the suspension.
8. Support the truck crane with the outrigger span required
for the job according to the Lifting capacity table and
raise until none of the wheels is touching the ground.
9. Align the truck crane horizontally (Figure 6-16).
10. Switch the engine off.
11. Inspect the truck crane, while looking out in particular for
any leaking fluids (oil, fuel or water).
12. Extend the step (Figure 6-17) if necessary, refer to
Superstructure Cab Platform, page 4-34.
13. Start the engine for crane operation.
14. Unlock the turntable and if necessary switch off the 360°
lock, refer to Switching the 360° lock on/off, page 4-41.
Refer to Switching the 360° lock on/off, page 4-41.
15. If necessary reeve the hook block then pick up the hook
block;
- Hook block on a separate vehicle, page 6-30,
- Hook block on the bumper, page 6-30,
- Reeving the hoist rope, page 6-32.
16. Install the anti-two block switch, refer to Installing/
removing the anti-two block switch, page 6-36.
17. Install the anemometer and if necessary the boom
position indicator light;
Anemometer and boom position indicator light, page 6-
40.
18. Fold out and adjust all mirrors for crane operation.
19. Perform all the required checks prior to crane operation,
refer to Before operating the crane
, page 4-37.
FIGURE 6-16
8856-20d
FIGURE 6-17
8852-2

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc Grove TMS9000-2 Series and is the answer not in the manual?

Manitowoc Grove TMS9000-2 Series Specifications

General IconGeneral
BrandManitowoc
ModelGrove TMS9000-2 Series
CategoryConstruction Equipment
LanguageEnglish

Related product manuals