4-55
TMS9000-2 OPERATOR MANUAL OPERATING PROCEDURES
Published 02-21-2019, Control # 611-05
NOTE: The raising of the main boom will be shut down if
the main boom angle is too great. Then all you can
do is set the load down.
Switch off function
• Release switch 1 in Figure 4-82.
In emergencies
During this type of override, the complete shutdown of the
RCL is canceled and no monitoring takes place.
Canceling a shutdown
• Insert the key into the key-operated switch (1,
Figure 4-83).
• Turn the key to the left or right once.
- All crane movements are enabled for 30 minutes.
- The status display (2) will flash red.
Canceling the override
The override will be canceled when you:
- Switch off the ignition
- Press the key-operated switch again.
The override will automatically be canceled 30 minutes after
the key-operated switch has been pressed.
Crane operation with main boom
Ensure the crane is level before lifting operation begins.
If the crane is found to be out of level during operation, stop
operation, set the load down, return the boom to the travel
position and re-level the crane.
Main hoist
You can reeve the hoist rope of the main hoist on the main
boom or on the lattice extension.
WARNING
Rope Damage Hazard!
Use of hookblocks that do not have sufficient overhaul
weight could result in spooling problems causing damage
to the rope. Death or Serious injury could occur if the rope
breaks. Always ensure that the overhaul weight is
sufficient to keep tension on the rope even when no load
is being lifted.