10 Fault elimination
Maschinenfabrik Reinhausen GmbH 2020 3636385142/08 EN ETOS
®
ED
Characteristics/details Cause Remedy
Plan oil filter replacement
Event No. 1165
The limit value for maintenance
has been reached.
Signal at X1:105 and 900 tap-
change operations made
Carry out maintenance work and then confirm
this in the visualization.
Maintenance work has been car-
ried out but not confirmed in the vi-
sualization.
Confirm maintenance work in the visualization.
Wiring error Check the wiring of terminals X1:105/106.
Replacement or change of con-
tacts is required
Event No. 1168
The limit value for maintenance
has been reached.
Carry out maintenance work and then confirm
this in the visualization.
Maintenance work has been car-
ried out but not confirmed in the vi-
sualization.
Confirm maintenance work in the visualization.
Load current measurement faulty. Check measured values.
Check the wiring of the assembly for load cur-
rent measuring (UI or AIO).
Maintenance data incorrect Call up the maintenance log and check the
date of the last maintenance work.
Plan replacement or change of
contacts
Event No. 1167
The limit value for planning mainte-
nance has been reached.
Plan maintenance and carry out maintenance
work soon, and then confirm this in the visual-
ization.
Maintenance work has been car-
ried out but not confirmed in the vi-
sualization.
Confirm maintenance work in the visualization.
Load current measurement faulty. Check measured values.
Check the wiring of the assembly for load cur-
rent measuring (UI or AIO).
Maintenance data incorrect Call up the maintenance log and check the
date of the last maintenance work.
OLTC must be replaced
Event No. 1148
The limit value for maintenance
has been reached.
Carry out maintenance work and then confirm
this in the visualization.
Maintenance work has been car-
ried out but not confirmed in the vi-
sualization.
Confirm maintenance work in the visualization.
Maintenance data incorrect Call up the maintenance log and check the
date of the last maintenance work.
Plan OLTC replacement
Event No. 1147
The limit value for planning mainte-
nance has been reached.
Plan maintenance and carry out maintenance
work soon, and then confirm this in the visual-
ization.
Maintenance work has been car-
ried out but not confirmed in the vi-
sualization.
Confirm maintenance work in the visualization.
Maintenance data incorrect Call up the maintenance log and check the
date of the last maintenance work.
Table133: Maintenance messages