Recipes
RECIPE 1 05.09.05 TEXT 1
RECIPE 2 07.09.05 TEXT 2
File: Description:
RECIPE 3
Operation
4‐11
P/N 213828_11
2014 Nordson Corporation
VersaBlue_PPA
Note on Recipes
Process parameters can be saved on the melter memory board as a file
(recipe) and then backed up onto an external PC from there.
Refer to Operation via the IPC Webserver for additional information.
After the First Day
CAUTION: Heating and cooling that occur during daily operation can cause
screwed parts to loosen, resulting in leakage.
12. After the first day, while the material is still soft (approx. 70°C/158°F,
depending on the material), retighten the following:
Safety valve
Pressure sensors (when applicable)
Plug
Hose connections.
Then check at regular intervals and repeat as required. Refer to section
Maintenance.