AccessNode Series 800A Outside Plant Cabinet Installation 323-3001-210 Issue 1.0
1-1
Installing the pad 1-
This
chapter contains procedures for the site preparation and installation of
the AccessNode Series 800A cabinet. The chapter gives information for:
• planning site selection and preparation
• determining cabinet placement
• preparing the cabinet mounting pad
• pouring the concrete
How to use this chapter
In the following table, you will find a list of the procedures to install the
concrete pad for the AccessNode S800A Outside Plant cabinet. Perform the
procedures in the order listed. If you cannot successfully complete these
procedures, contact your next level of support.
Chapter task list
This chapter provides the procedures for the tasks presented in the table below.
Task See
Preparing the poured-in-place cabinet mounting pad Procedure 1-1 on page 1-8
Pouring the concrete Procedure 1-2 on page 1-23