2-16 Installing the cabinet
AccessNode 323-3001-210 Issue 1.0
Procedure 2-3 (continued)
Preparing the cabinet for installation
Crane operation precautions
Adhere to all local, state, and federal safety standards for crane operations.
Ensure the following guidelines are observed:
• Set up the crane on firm footing.
• Extend the outriggers, block the floaters and insert safety pins.
• Ensure that the crane is “off rubber” during the lift.
• Ensure that the crane is level before lifting to eliminate tipping.
• Do not place any body part underneath the load at any time and do not
stand on the load.
• Use tag lines to maneuver the load.
Eyebolt precautions
Before lifting cabinet, ensure that eyebolts are free of the following visible
defects:
• bent or distorted eye or shank
• obvious wear
• worn and/or distorted threads
• cracks
Cabinet weights
Table 2-6 lists the weight of the S800A cabinets equipped with each of the two
optional roof assemblies.
—continued—
Table 2-6
Cabinet weights
Cabinet (without batteries) Weight
Equipped with air induction roof 2000 lb (907.2 kg)
Equipped with heat exchanger roof 2200 lb (997.9 kg)