Installing the cabinet 2-17
AccessNode Series 800A Outside Plant Cabinet Installation 323-3001-210 Issue 1.0
Procedure 2-3 (continued)
Preparing the cabinet for installation
Prerequisites for installation
The operating company is responsible for the choice of site and compliance
with local regulations such as the applicable electrical codes, right-of-way
easements, and noise requirements.
Installation procedures assume the following:
• All hardware and materials are available, and have been checked for
completeness and readiness for the installation.
• The correct cabinet pad has been poured and cured at the site.
• The cabinet pad has been prepared as described in Chapter 1, “Installing
the pad.”
• All the required drawings, local installation instructions, job
specifications, and other documentation are available and ready for use.
• Procedure 2-1 on page 2-7, “Unpacking the cabinet” has been completed.
• Procedure 2-2 on page 2-10, “Preparing the pad” has been completed.
—continued—