AccessNode Series 800A Outside Plant Cabinet Installation 323-3001-210 Issue 1.0
4-1
Installing the OSP cables 4-
This chapter provides information on the routing and installation of the
external cabling into the S800A cabinet. Voice frequency (VF), miscellaneous,
T1, fiber and maintenance cabling enters the cabinet through the termination
compartment.
How to use this chapter
In the following table, you will find a list of the procedures to install the
external outside plant cabling for the AccessNode S800A Outside Plant (OSP)
cabinet. Perform the procedures in the order listed. If you cannot successfully
complete these procedures, contact your next level of support.
Chapter task list
Task See
Pulling the OSP cabling into the cabinet Procedure 4-1 on page 4-4
Butting and stripping the VF, miscellaneous, T1
and maintenance cables
Procedure 4-2 on page 4-8
Butting and stripping the fiber cable Procedure 4-3 on page 4-12
Installing the cable bonding clamps Procedure 4-4 on page 4-16
Applying a moisture barrier to the air-core cable Procedure 4-5 on page 4-20