AccessNode Series 800A Outside Plant Cabinet Installation 323-3001-210 Issue 1.0
11-1
Finishing the S800A cabinet installation
procedures 11-
This section provides information for installing the protector modules into the
S800A cabinet and navigational information for performing commissioning
and site testing operations for the S800A cabinet.
Commissioning and Testing, Volume 3, provides procedures for
commissioning and testing the AccessNode system.
Note: These documents apply to all configurations of the AccessNode such
as bays or cabinets.
How to use this chapter
In the following table, you will find a list of the procedures for installing the
protector modules into the S800A cabinet and navigational information for
performing commissioning and site testing operations for the AccessNode
system. Perform the procedures in the order listed. If you cannot successfully
complete these procedures, contact your next level of support.
Chapter task list
Task See
Install the protector modules Procedure 11-1 on page 11-2
Perform the system commissioning and testing Procedure 11-2 on page 11-6
Installing the shipping brackets Procedure 11-3 on page 11-7