6-28
Batch
flexible
, Manual
C79000-G7076-C650-02
You can undo multiple allocations of equipment by changing the following
planning data:
S Assign the batch to another apparatus by selecting a different recipe, or
alternatively
S adjust the starting time of the batch.
S Another way is to adjust the equipment occupancy times in the control
recipe.
You can make these changes in the batch dialog or in the recipe parameters
dialog, as described in Chapter 6.3.2. You can open the batch dialog by
double-clicking on the corresponding line in the table.
Changing
equipment
occupancy
Batch planning