12 Decommissioning
12�1 Information about personnel and safety
The decommissioning of the plant is only allowed to be carried out by suitable, trained
personnel.
For damage due to incorrect performance TEKA Maschinenbau GmbH does not accept any
liability.
You must observe the stipulations of chapter "2 Safety" of these operating instructions.
12�2 Taking the machine out of operation
● Switch o the plant and plant parts.
● Switch o the units (hydraulics and lubrication).
● Cut o the supply of energy and operating materials.
● Dismantle the lines for the supply of energy and operating materials.
● Discharge excess energy capacities:
Vent the hydraulic system (units, pre-charged accumulators, lines, and hoses).
● Drain the tanks.
● Vent the lubrication system, drain the oil.
● Empty uid tanks and pressure vessels.
● Dismantle the plant.