上海维宏电子科技股份有限公司
SHANGHAI WEIHONG ELECTRONIC TECHNOLOGY CO., LTD.
76 / 131
3. Select order strategy and start position.
Color: used to specify the order of layers.
Machining order result shows as follows:
• Sheet cutting configuration
According to the selected order strategy and start point, the system generates
machining order automatically.
• Tube cutting configuration
– The system divides the machining object into some sections by break
line and machines from bottom to top by default.
– In each section, according to the selected order strategy and start point,
the system automatically generates machining order.
5.4.2 Manually Change the Machining Order
To manually change the machining order, do the following:
1. Do one of the following:
– In drawing toolbar, click .
– In menu bar, click Object → Mach Order → Manual Set.
– In drawing window, right click and select Manual Set Mach Order.
– In drawing window, select an object, right click and select Mach Order
→ Manual.
The cursor turns into , and the system automatically shows the machining
order.
2. Select the first target object.
The cursor turns into . The machining order on the object turns into 1, and
the order of other objects turns into 2,3 … in sequence on the basis of previous
order.
To reset the last order number, right click and select Previous Order.
3. Repeat step 2 and click the objects in order.
If you need to exit manual setting tool, do one of the following:
• Right click and select Exit.
• Press Esc.