7.1 Flow of Trial Operation
7.1.1 Flow of Trial Operation for Rotary Servomotors
7-2
7.1
Flow of Trial Operation
7.1.1
Flow of Trial Operation for Rotary Servomotors
The procedure for trial operation is given below.
Step Meaning Reference
Preparations for Trial Operation
1
Installation
Install the Servomotor and SERVOPACK
according to the installation conditions.
First, operation is checked with no load.
Do not connect the Servomotor to the
machine.
Chapter 3 SERVOPACK Installation
2
Wiring and Connections
Wire and connect the SERVOPACK. First,
Servomotor operation is checked without a
load. Do not connect the CN1 connector
on the SERVOPACK.
Chapter 4 Wiring and Connecting SERVOPACKs
3 Confirmations before Trial Operation
7.2 Inspections and Confirmations before Trial Opera-
tion on page 7-6
4Power ON −
5
Resetting the Absolute Encoder
This step is necessary only for a Servomo-
tor with an Absolute Encoder.
5.17 Resetting the Absolute Encoder on page 5-51
Trial Operation
6
Trial Operation for the Servomotor without
a Load
7.3 Trial Operation for the Servomotor without a Load
on page 7-7
7
Trial Operation from the Host Controller
for the Servomotor without a Load
7.4 Trial Operation from the Host Controller for the Ser-
vomotor without a Load on page 7-10
Continued on next page.
To power
supply
Secure the motor ange to the
machine. Do not connect the
motor shaft to the load shaft.
To power
supply
CN1, to host controller
Secure the motor ange to the
machine. Do not connect the
motor shaft to the load shaft.