Advant
®
Controller 450 User’s Guide
Chapter 2 Installation
2-56 3BSE 002 415R701 Rev A
If correct indications fail to appear, trace the fault in accordance with the instructions given in
Section 5.5, Fault Finding and User Repair.
2.4.2.2 Initialization
The power-up achieved by following the above instructions produces an automatic
initialization.
In general, you can start an Advant Controller 450 in four different ways, as selected with the
selector Start Mode on the processor module front. These ways and applications are described in
Chapter 4, Runtime Operation.
2.4.2.3 Connection of Engineering Station
If it is not installed during the setup phase (see Section 2.2.14, Engineering Station), you can
plug the engineering station communication cable into the service port X10 on the
Processor Module PM511 front at any time.
• First connect the communication cable.
• Then switch on the power supply to the engineering tool.
Prepare for a session of programming Advant Controller 450.
Follow the instructions on the screen.
Work with the engineering station is supported by adequate documentation.
For detailed information about different configuration activities using an engineering tool,
see the manual AMPL Configuration Advant Controller 400 Series.
If the actual Advant Controller 450 is a node in a LAN, you can connect the engineering station
to any of the nodes included in the network. You can perform remote configuration in that way.
Figure 2-25. Power-up, Circuit Breakers and Positive Indications
.
Controller cabinet
SR511
Green LEDs, 5 V and 2 V
SX554
Green LED, LIVE (24 V)
P2
PM511
Display
Circuit breaker(s)
S1, F1
Green LED, RUN
SB511
Green LED, IP