Refitting SMB battery
Use this procedure to refit the SMB battery.
NoteAction
DANGER
Turn off all:
electric power supply
hydraulic pressure supply
to the robot, before entering the robot working area.
1
ELECTROSTATIC DISCHARGE (ESD)
The unit is sensitive to ESD. Before handling the
unit please read the safety information in the section
The unit is sensitive to ESD on page 31
2
See the figure in Location of SMB
battery on page 186.
Reconnect the battery cable to the SMB battery.3
See the figure in Location of SMB
battery on page 186.
Put the battery unit into its recess while arranging
the SMB cables as shown in the figure.
4
See the figure in Location of SMB
battery on page 186.
Secure the SMB cover with its attachment screws.5
Seal and paint the joints that have been opened.
Also repair possible damages of the special Foundry
Prime paint coat of the robot. See Cut the paint or
surface on the robot before replacing parts on
page 201.
6
Detailed in Updating revolution
counters on page 360.
Update the revolution counter.7
DANGER
Make sure all safety requirements are met when
performing the first test run. These are further de-
tailed in the section First test run may cause injury
or damage on page 26.
8
Product manual - IRB 4600 Foundry Prime 189
3HAC040585-001 Revision: M
© Copyright 2013-2018 ABB. All rights reserved.
3 Maintenance
3.5.8 Replacing SMB battery
Continued

Table of Contents

Related product manuals