xx1400000522
DescriptionItem
Cable tray, 1 mA
External chain raiserB
External tray 1.45 m unitC
External tray bracket unitD
Plan the job
Cable chains are easily damaged through improper handling. Chains longer than
4 meters are heavy and cumbersome to move. In order to prevent personal injury
and damage to the chain, make sure to pay attention while handling.
Read the procedure thoroughly before installing the chain and plan the job in
advance, in regard to the actual installation site.
To move the chain from storage to track, use one of the methods described in this
section. Method 2 requires an overhead crane.
Required equipment
NoteArt. No.Equipment
Quantity depends on track length.-Lifting slings, standard
Required if using lifting method 1.
Required if using lifting method 2.-Lifting sling, extra wide (50 mm)
-Overhead crane
Continues on next page
60 Product manual - IRBT 2005
3HAC051130-001 Revision: F
© Copyright 2015 - 2018 ABB. All rights reserved.
2 Installation and commissioning
2.3.4.4 Lifting cable chain
Continued