2.4.5 Assembling the sections of the track motion IRBT 2005 (Longer than 9 m)
Required equipment
Standard tools
ToolQuantity
Ring-open-end spanner 8 - 22 mm1
Small flat tip screwdriver1
Torque wrench 10 -140 Nm1
Ratchet head for torque wrench 1/2"1
Special tools
IllustrationArt. No.DescriptionQuantity
-Rack clamps2
3HAC054535-001Leveling tool1
3HAC054534-001Locking nut adjust-
ment tool
1
Continues on next page
Product manual - IRBT 2005 83
3HAC051130-001 Revision: F
© Copyright 2015 - 2018 ABB. All rights reserved.
2 Installation and commissioning
2.4.5 Assembling the sections of the track motion IRBT 2005 (Longer than 9 m)