3. Have another person hold the switch at the desired location in the
equipment rack while you secure it using four standard equipment rack
screws (not provided). Refer to Figure 41.
Figure 41. Installing the Switch in an Equipment Rack
4. Install the other switches of the stack.
5. After installing the switches, go to Chapter 7, “Building the Trunk with
the Default SFP+ S1 and S2 10Gbps Stacking Ports” on page 131 or
Chapter 8, “Building the Stack with Gigabit or 5G Multi-speed Ports” on
page 149.