Testing
9.1 Requirements for tests and measurements
5284 / 08/2023 en BENNING ST 755+ / ST 760+ 71
9 Testing
9.1
Requirements for tests and measurements
Please observe the following basic requirements for tests and measurements:
During initial commissioning before carrying out the first test: Calibrate the device using the
internal calibration (zero balance, cable and probe calibration) [}page69].
Only use approved safety measuring lines [}page74].
Disconnect any safety measuring lines not required for the respective test or measurement
from the device.
Please consider sources of interference that might be present. Strong sources of
interference in the vicinity of the device might involve unstable readings and measuring
errors.
For carrying out the tests and measurements, please observe the associated measuring
ranges and measuring accuracies stated in the chapter “Measuring ranges”.
Please observe the figures for the corresponding test setup.
Please note that if the test is interrupted or paused, the testing voltage is still applied.
Determine the necessary measuring points before starting the test.
Follow the instructions on the display of the device.
Make sure that you are familiar with the general operation of the device [}page27].
A test sample may only be electrically tested if no serious defects have been detected
during the visual inspection.
Please observe applicable regulations from the current VDE/ ENstandard.
Please observe the manufacturer's specifications in the accompanying documents of the
test sample before starting a test as well as during the test.
The cables of the test sample must be completely unreeled, e.g. in case of cable reels.
For the testing of test samples with the warning “High leakage current!”, the test must be
carried out by qualified electricians only!
Specification, selection and order of individual tests are determined by the responsible
qualified electrician.
The limits preset in the factory correspond to the normative specifications that have been
applicable at the time of printing. Administration and definition of the customer-specific limits
shall be at the discretion of the qualified electrician carrying out the work.
For test samples with protective measures regarding the protective conductor: Test the test
sample in all switch positions (test sample functions).
Dangerous voltages might occur on the test sample during insulating resistance
measurement (R
Insu
) or when using the alternative leakage current measuring method.
For device protection and for functional testing, the test voltages are monitored. In case of a
fault, an error will be indicated on the display. Measurement will be interrupted. In case of a
fault current of ≥25mA, the device will be switched off within a period of 100ms to 200ms.
Only carry out PRCDtests without load.
In order to detect short-circuits and body contacts occurring behind the switch-on elements
(e.g. switch, thermostat, relay) of the test sample, the test sample must be switched on.
The jacks "L", "N" and "PE" are connected to the test socket. If mains voltage is applied to
the test socket, the connection will be disconnected.
Tap the “Pause” button to interrupt the measurement. During the pause, the test socket
remains live!