88
20.7 Road File Management
20.7.1 Select a Road File
All the elements you inputted and the staking data you calculated are recorded in the
current road file. You can select other file to define other road, normally one file includes
one road.
NOTE:
There are 10 road files in total, the factory default setting is “ROAD1”.
The default names are “ROAD1”,”ROAD2”…”ROAD10”, you can rename them if
necessary.
Procedures:
1. Press F2: [MENU] on P2 of the basic measurement
mode, on the page 3 select 1.Road Calculation enter
road menu.
2. Select 3.Road file to road file management menu.
3. Select 1.Road File Select to display road file list,
the cursor will stay on current Job file.
4. Press or arrow key to move cursor, after reach to the
job you want to select, press [ENT] key to confirm. The
program will back to road file management menu
automatically.
Road Calculation
1.Input the parameter
2.Road Setout
3.Road file
Road file
1.Road File Select
2.Road File Rename
3.Road File Delete
4.Road Initialize
Road File Select P1
ROAD1 96
ROAD2 55
ROAD3 0
ROAD4 0
ROAD5 0
ROAD6 0
ROAD7 10
Road File Select P1
ROAD1 96
ROAD2 55
ROAD3 0
ROAD4 0
ROAD5 0
ROAD6 0
ROAD7 10

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Foif RTS680 Series and is the answer not in the manual?

Foif RTS680 Series Specifications

General IconGeneral
BrandFoif
ModelRTS680 Series
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals