Page 74 
Example 1 ‘V’ Notch   Weir 
 
 
The application is to be assigned to Point (transducer) 1. 
In  this  example  it  is  required  to  calculate  the  flow  through  a  Simple 
Exponential Device, which on this occasion is a V-Notch Weir. The K factor 
for the weir is unknown so ratiometric calculation will be used, and the flow 
rate is to be calculated in millions of US gallons/day.  
The distance from the end of the transducer horn (dB Mach 3) to zero flow 
(P105)  is 40  inches  and  max head  (P704)  is  15 inches,  maximum flow 
(P705) is known to be 2.2million US gallons/day.