1. Turn onMain Power On/Off”. The switch will be green when powered on.
2. Ensure the SCV supplying system pressure to the block is activated and locked into constant
flow. The pressure needs to be adjusted from your tractor to fall within 2500-2900 PSI.
3. Once your drill has been unfolded from the transport position, you are ready to begin seeding.
4. Using the SCV connected to your opener lift/lower lines, lower the openers into the ground. Set
this SCV at a flow of 75% to ensure the lift and lower speeds are adequate and set a timer to
help ensure that the SCV returns to neutral after the openers have lowered.
5. When the openers begin to build pressure on the Opener Down Pressure gauge, return the
SCV to neutral if it is not set up as timed.
6. Turn on the “Opener Pressure On/Off” switch. The switch will be green when powered on.
7. When entering a headland, turn the “Opener Pressure On/Off” switch off.
8. Lift the openers with the SCV connected to your opener lift/lower lines.
9. Complete the turn.
10. Repeat steps 4, 5, and 6 to resume seeding.
NOTE: Always ensure the Opener Pressure On/Off switch is in the “off” position before
attempting to lift the openers. Failure to do this will result in the wings lifting, and the
openers dropping prematurely.