Commissioning
5.2 Basic commissioning
SINAMICS G110M Operating Instructions
Operating Instructions, 04/2015, FW V4.7.3, A5E31298649B AD
93
Basic Commissioning with DIP switches
Overview
The CU240M Control Units have been designed to allow basic commissioning to be
performed using a set of three DIP switches. The DIP switches are located on the
communications board within the Control Unit housing, as shown in the figure below.
Figure 5-4 DIP Switches location