On Pass/Fail Pause
The two pause lines determine if the test will continue automatically or
pause and wait for an operator input before continuing. A pause can be a
useful option. It can allow time for an operator action to be performed
before the test continues. The operator must hit the START switch before
the test sequence will continue.
The pause can be set to YES active or NO inactive. The pause only occurs
if the associated Program value is also active (not zero). For example: if
the On Pass Program is set to zero and the test passes, the test will end
and there will be no pause. (Even if the On Pass Pause is set to YES.)
Next Program Sub-Parameter Menu
Back Prev Next Inc Dec
PROGRAM 1
Test Type PD
Test Press. 10.000 psig
Press. Error .5 psig
Coupling GoTo
Test Params GoTo
Next Program 0
Next Program Setup
On Pass
Program 2
Pause YES
On Fail
Program 0
Pause NO
FIGURE 96