Page 82
Test Result Report
The Test Results report is sent automatically at the conclusion of each test.
There is no need to press any keypad to send a serial string via the RS-232
port. A sample Test Result report is shown below. The number in the
column under “cycle” is the counter for that particular run. The columns
are tab delimited and can be imported into any spreadsheet program. As
explained previously, the heading for each column is provided by the
Parameter List and Test Result Heading.
The Test Results report prints one test program at a time. In the example
below, first two test cycles were run on Program 1. Then the current
program was changed to Program 2 and two test cycles were run. Finally
two test cycle were run on Program 3.
Example Result Report
Cycle Prog Test Value Units Result
1 1 PD .005 PSIG PASS
2 1 PD .055 PSIG LEAK
1 2 Flow 110.12 SCCM PASS
2 2 Flow 180.03 SCCM HIGH
1 3 BURST 4.005 PSIG PASS
2 3 BURST .355 PSIG LOW
Tested Count
The Sprint stores a separate count for each test
program. The cycle number in this report matches
the Tested box count number in the run display.