36 ACF5000 FTIR ANALYZER SYSTEM | OI/ACF5000-EN REV. A
"2nd measuring location" option
Installing the electrical distributor cabinet
The electrical distributor cabinet for connecting the 2nd measuring location
must be installed as close to the analyzer cabinet as possible.
On the analyzer cabinet, cables of about 5 m in length are applied for con-
nection to the electric distribution cabinet.
Installing the heated switchover valve
The heated 3/2-way solenoid valve for switching between the two measur-
ing locations must be assembled as close to the analyzer cabinet as possi-
ble.
The sample gas lines from the two sampling points and the 1.5 m sample gas
line to the analyzer cabinet must be connected to the switchover valve. Dur-
ing installation of the sample gas lines, the information in the section "In-
stalling the sample gas line" (see page 40) must be observed.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB ACF5000 and is the answer not in the manual?

ABB ACF5000 Specifications

General IconGeneral
BrandABB
ModelACF5000
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals