150
Winder
Basic commissioning
Before starting the winder commissioning following steps have to be done first:
1. Basic commissioning steps 1 to 5 with a freely turning machine, no mechanics connected:
2. Basic commissioning steps 6 and 7 with a freely turning machine, gearbox and spool connected, no web:
Advanced commissioning
1. Set all necessary protections and limits, make sure the E-stop / el. Disconnect is working properly and
connect the overriding control system (serial communication):