Basic commissioning 
Before starting the winder commissioning following steps have to be done first: 
1.  Basic commissioning steps 1 to 5 with a freely turning machine, no mechanics connected: 
 
2.  Basic commissioning steps 6 and 7 with a freely turning machine, gearbox and spool connected, no web: 
 
Advanced commissioning 
1.  Set all necessary protections and limits, make sure the E-stop / el. Disconnect is working properly and 
connect the overriding control system (serial communication):