2. Project management
2−15
Festo P.BE−SPC200−WIN−PISA−CD−EN en 0901d
The following conditions must be met for a complete project
to be downloaded to the SPC200:
The project must be compiled free of errors,
The hardware configuration set in the project must
correspond to the actual hardware configuration of the
SPC200.
When a project is downloaded, all the data will be restored as
in
the project in the SPC200. This means that any programs in
the SPC200 will be deleted if they do not exist in the project.
Please note
Check the programs in the SPC200 before a project
download.
In order to load a project into the SPC200, this must be con
nected to the PC (see Online mode).
To download a project to the SPC200:
1. Activate the Online mode from the [Online] menu using
the [Online mode] item or click
on the Online mode on"
button on the toolbar.
2. Select [Project] from the [Online] [Download] menu.
The progress of data transmission is shown in a Window as
the project is being downloaded to the SPC200. The two bars
show the progress of transmission as a percentage. The
upper bar represents the complete project, the
lower one
shows the project component currently being transmitted.
This is shown under Load".
3. Confirm successful transmission with OK".
Confirm the prompt and repeat the process should an error
occur during transmission.