EasyManua.ls Logo

Festo SPC200 - Guidelines

Festo SPC200
404 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Contents and general instructions
XXVII
Festo P.BE−SPC200−WIN−PISA−CD−EN en 0901d
Guidelines
WinPISA permits various procedures for creating projects and
for commissioning the SPC200. A large number of functions
are available, the use of which is not absolutely necessary.
This section is intended as a guideline. It shows a logical pro
cedure for generating and commissioning projects and indi
cates the functions required. It is
assumed that your position
ing system is correctly connected to the PC and is ready for
operation.
Further information on commissioning the positioning system
can be found in the manuals and descriptions for the SPC200
(see section Documentation on positioning").
Preparing the SPC200
Create the hardware configuration
Mount the components as described in the SPC200 manual.
In order to commission the axes, you must first create the
desired configuration on the SPC200.
Preparing the PC
Start and configure WinPISA
(see also sections 1.1, 1.2 and 1.7)
1. Please observe the current information in the file
README.TXT in subdirectory \BIN of the WinPISA
installation directory.
2. Start WinPISA.

Table of Contents

Other manuals for Festo SPC200

Related product manuals