8.3  Installation 
This Section explains how to install the Hydran 201Ci-C Controller. 
Read  all  the  warnings  and  recommendations  in  Section  6.1 
(General Warnings) before proceeding with the installation. 
Note:    It  is  strongly  recommended  that  the  operation  of  all  H201Ti’s  and  H201Ci 
Controllers  be  verified  before  installation  of  the  equipment  in  the  field.  Verification  also 
allows the user to become familiar with the Hydran 201i System. 
All procedures in this manual must be strictly adhered to.  Any 
deviation  from  these  could  cause  irreversible  damage  to  the 
transformer being monitored and/or the Hydran 201 i System, 
and  could  lead  to  property  damage,  personal  injury  and/or 
death. 
Installation and maintenance of the  Hydran 201i System must 
be carried out by qualified personnel only. 
The H201Ci-C is equipped with a Type NEMA 4X enclosure and internal heating; it can 
thus be installed outdoor. 
 
8.3.1  Verifying the AC Power Supply Voltage and the Serial Numbers 
Ensure steps 3 and 4 on page 122 have been performed.  
 
8.3.2  Installing the Enclosure 
Prepare  the  installation  location  of  the  Hydran  201Ci-C.    Read  the  recommend-
dations in Section 6.2.3. 
The  H201Ci-C  must  be  mounted  on  a  vibration-free  structure.    If  vibrations  are 
present, use vibration-absorbing rubber pads (Figure 2-5), which can be purchased from 
General Electric. 
 
8.3.3  Installing the Cable Conduits 
Note the following considerations prior to installing: 
•  All cables connected to the Hydran 201Ci-C must be run through steel conduits.  
Otherwise, armored cables can be used.