Page 38 of 101 Rev.: 001
BL 121 EN Translation of the original operating manual 2011 / 05
Safety rails on-site may only be removed once the landing-level
safety gates have been installed.
The hoist may only be operated once all landing-level safety de-
vices have been fully installed and checked.
7.4 First commissioning / daily commissioning
Make sure that:
All safety features are present and functioning.
All connections are properly connected.
All parts are correctly installed.
No tools or other parts are inside or on the machine.
No tools or other parts are in the travel path of the machine.
All warning and instruction notices on the machine are present in
their entirety, are clearly visible and undamaged.
Illegible or missing warning and instruction notices must be re-
placed immediately.
The tests specified in national regulations must be performed prior
to commissioning.