15.2 Assembly plan
The assembly is generally carried out in accordance with the following
schematic.
Assembly schematic
1. Erecting the base unit
1. Align
2. Bolt support plates to the foundation
3. Connect to the mains electricity supply of the operating com-
pany
2. Assembling the mast
1. Bolt the mast elements together
2. Set the anchoring points
3. Align the mast
3. Set the EMERGENCY limit switch bar
4. Secure the loading points using landing-level equipment
5. Check the machine for initial operation
6. Train authorized personnel