363-206-285 Circuit Order: NTP-031
Issue 2, February 2000 Page 4 of 6
DDM-2000 OC-3 MULTIPLEXER
DO ITEMS BELOW IN ORDER LISTED . . . . .FOR DETAILS, GO TO
NOTE:
The following commands may be used to convert, delete,
enter, and retrieve cross-connections: cnvt-crs,
dlt-crs-sts1, dlt-crs-vt1, ent-crs-sts1,
ent-crs-vt1, rtrv-crs-sts1, and rtrv-crs-vt1.
See the Commands and Reports section of this manual for a
description of commands. See Cross-Connection
Provisioning in the Administration and Provisioning section
of this manual for more information on cross-connection
provisioning.
Determine the necessary cross-connections for each node from
the work order or circuit order.
12. Make necessary VT1.5/STS1 cross-connections at each node in
the network.
DLP-546A. Single Ring Configuration
DLP-550B. Dual Ring Interworking (DRI) Configuration
DLP-559C. Single/Dual OC-3 & OC-12/OC-48 Configuration
DLP-560D. Single/Dual OC-3/OC-12 Configuration
13. Use the opr-lpbk-t1: command to loopback the DS1s at the
far end.
14. Use the rtrv-pm-lan: command to determine the
performance of the IMA LAN circuit pack being established.
15. Use the rls-lpbk-t1: command to release the DS1 loopback
at the far end.
16. Verify that no LEDs or alarms are activated. If any LEDs or alarms
are activated, refer to Trouble Clearing: IXL-001 and follow the
appropriate trouble-clearing procedure.
17. Use the rtrv-state-eqpt: command to determine the port
state of the LAN port(s) of the circuit being established.
DLP-546
DLP-550
DLP-559
DLP-560