EasyManuals Logo

Nortel SONET AccessNode 800A Series User Manual

Nortel SONET AccessNode 800A Series
450 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #102 background imageLoading...
Page #102 background image
4-6 Installing the OSP cables
AccessNode 323-3001-210 Issue 1.0
Procedure 4-1 (continued)
Pulling the OSP cabling into the cabinet
Step Action
9 Perform the steps shown in Table 4-3 for the fiber entrance arrangement
dictated by the job specifications.
10 Secure the cable in an out-of-the-way position.
—continued—
Table 4-3
Pulling the OSP fiber into the cabinet
If the job specifications
require that the OSP
fiber cable is to be Then perform these steps
Spliced, grounded and
bonded in a location
external to the S800A
cabinet
• Protect the entire length of the fiber patch cords with
split flex tubing, or by using standard local practices
prior to pulling them into the cabinet.
• Pull the protected fiber patch cords from the external
source into the cabinet through the conduit opening
located on the far right-hand side of the termination
compartment (see Figure 4-1 on page 4-7).
• Tie wrap the protective tubing, with the patch cords
inside, to the rungs of the cable ladder on the right
hand side of the termination compartment.
• Go to step 10.
Spliced, grounded and
bonded at a fiber
management system
internal to the S800A
cabinet
• Pull the OSP fiber cable into the cabinet through the
conduit opening located on the far right-hand side of
the termination compartment
(see Figure 4-1 on page 4-7).
Note:
Splicing, bonding and grounding will be done at
the fiber management system (see Chapter 7,
“Routing and splicing the fiber cable”).
• Go to step 10.
Spliced at the fiber
management system and
bonded and grounded at
the termination
compartment in the
S800A cabinet
Pull the OSP fiber cable into the cabinet through the
conduit opening located on the far right-hand side of
the termination compartment
(see Figure 4-1 on page 4-7).
Note:
Bonding and grounding procedures are in
Procedure 4-3 and Procedure 4-4 of this practice.
Splicing will be done at the fiber management system
(see Chapter 7, “Routing and splicing the fiber cable”).
• Go to step 10.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Nortel SONET AccessNode 800A Series and is the answer not in the manual?

Nortel SONET AccessNode 800A Series Specifications

General IconGeneral
BrandNortel
ModelSONET AccessNode 800A Series
CategoryNetwork Hardware
LanguageEnglish

Related product manuals