7. Attach the cable box cover to the front cover.
8. Install the cable box to the frame. Position the cable box (8a) and tighten the
screws (8b).
6a
6b
8b
8b
6 7 8
8a
Note: Install the hood to UL Type 12 drives after you have installed the drive
electrically and reinstalled covers, see Installing UL Type 12 hood (page 212).
Installing the drive vertically, frame R5
Select fasteners and their application to meet local requirements appropriate to
wall surface materials, drive weight and application.
1. Mark the hole locations using the mounting template included in the package.
Do not leave the mounting template under the drive. The drive dimensions
and hole locations are also shown in the drawings in chapter Dimension
drawings (page 363).
2. Drill the mounting holes.
3. Insert fixing anchors or plugs into the holes. Start the two upper bolts and the
two lowest bolts into the anchors or plugs.
88 Mechanical installation