5-19
Component Identification Operator Manual P129394-176
DRAIN – Boiler drain opens, allowing water to drain.
NOTE: Heater elements are OFF during Drain phase.
FLUSH – Water flows through the boiler chamber for 5, 10 or 15
minutes as selected by the user (see Section 7.5.4, Steam
Generator Flush and Drain Set Up on page 7-20).
Once FLUSH is complete, the boiler chamber fills and reheats
water. Approximately 10 - 15 minutes are required to build a
head of steam suitable for running a sterilization cycle.
STATUS . .DRAIN 0:00 4
TEMP . . .00 F
PRESS . . .0.0 inHg
GENERATOR FLUSH
PROJECTED CYCLE COMPLETION TIME:
12:20
MINUTES SECONDS
PAPER STATUS
FEED PRINT
ABORT
STATUS . .FLUSH 0:00 4
TEMP . . .00 F
PRESS . . .00 inHg
GENERATOR FLUSH
PROJECTED CYCLE COMPLETION TIME:
05:20
MINUTES SECONDS
PAPER STATUS
FEED PRINT
ABORT