Programming Focus 61 Focus 61 User Guide
9839 0211 01 Edition 2.0 60 (118)
Timeout [s]
Maximum time (in seconds) of the measurement (starting from the moment that the torque reaches
the Cycle Start value).
The tightening operation should be completed before the timeout:
If the timeout is too short (or the tightening too long) the result might not be taken at the proper
maximum point:
NOTE: When a tightening operation is aborted because of a timeout, the result status
will be marked as TOK or TNOK, depending on whether the maximum torque was
inside the specified limits.
Dead Time [s]
Minimum time (in seconds) between two tightening operations. This timer starts when the torque
goes below the Cycle Start value.
Start the new tightening operation after the Dead Time expires:
A
Torque
B
Timeout
C
Time
A
Torque
B
Cycle Start
C
Timeout
D
Time
A
Torque
B
Cycle Start
C
Timeout
D
Dead Time
E
Time
F
Result 2
G
Result 1
A
E
B
C
D
G
F
B
A
C
D
C
B
A