CHAPTER 4 – Installation
Chap. 4
- 11/20 -
4.3 Preparing the machine for shipment
4.3.1 Disconnecting the electrical cabinet
STEP ACTION DESCRIPTION
1
Safety checks
Before working on any machine circuit or component, it is
OBLIGATORY to always verify that there is no residual voltage or
pressure in the systems, making sure that work is carried out safely and
that all safety devices are in place and working. Also make sure that all
personnel in the vicinity have been warned of the work being carried
out.
Check that all operators are in a safe position and aware of the work
being carried out.
2
Warnings /
Precautions
Danger of bumping into the structure and machine parts. Move
cautiously during inspection work.
Danger of slipping, tripping and falling inside the machine.
Move cautiously during work.
2
Disconnecting
machine wires
Some electrical connections between the electrical cabinet and the
various machine parts may have been made using cables that are wired
directly onto the components (1) (for ex. inverter) or present on the low
terminal board (2).
Disconnect the electrical wires checking that all connectors/wires are
numbered. If necessary, mark the rout of the wires.
Consult the wiring diagram in ANNEX A SYSTEM DIAGRAMS.
1
2