Preparation
Use only cleaned and disinfected parts!
Connecting the gas supply
1 Screw the central gas supply pressure hoses for O2,
AIR and N2O into the ports on the back of the gas
supply block.
The two ports at the front are reserved for the backup
gas cylinders.
2 The vacuum supply block (VAC) is available as option
for secretion aspiration.
Plug the other end of the pressure hoses into the wall
supply points.
Make sure the gas pressures of the central gas
supply are between 2.7 and 5.5 bar:
3 All three pressure gauges in the green zone.
22
Preparation
Connecting the gas supply
N2O AIR O2 VAC
12
Julian
D
3
"Only for internal use by Draeger. Not applicable as Instructions for Use!"

Table of Contents

Other manuals for Dräger Julian

Related product manuals