Performing a Site Survey
Perform a site survey to gather measurements necessary to determine sensor count, lens type, and
mounting location. Site surveys mitigate risk encountered during installation. An estimate can be
determined given a scaled floor plan and ceiling height at potential sensor mounting location. A site
survey is especially important for a new site design where sites with similar designs do not exist in a
customer blueprint database.
Preparing for a site survey
Follow these steps when planning a site survey:
1. Coordinate and schedule an on-site visit.
2. Gather all available information prior to going on site.
3. Establish site access protocols and any special conditions that must be followed to physically
visit the location.
4. Review project requirements, needed coverage areas, and network connectivity strategy.
5. Review the mounting options, as described in the following section.
Types of mounts
Mount types required for each sensor installation at a site are identified in the Site Installation
Specification.
The following is a description of mounts used with the 3D Gen 2 sensor.
Mount
Type
Application Examples
Surface
The 3D Gen 2 sensor has an integrated surface
mounting bracket which requires no separate
hardware. It can easily be affixed to the ceiling, and
allows the for the cabling to be hidden through the
back of device for a clean appearance. External side
wiring is also possible.
(A) If installing below a wooden joist, use two No. 8
(5mm) type screws, one for the center and one on
any of the four corners.
(B)If installing below a dry wall, use four No. 8
(5mm) screws, one in each corner.
A
B