Verifying the Solution Design
Before beginning the installation process, perform the following steps to verify the design solution for
quality assurance:
1. Confirm that the design has the same information as the Site Survey Output (e.g. ceiling heights,
number of doors, or checkout lanes).
2. Confirm that each sensor is being installed within allowable specifications for the chosen lens
type at the identified height of installation.
3. Confirm that the coverage area defined for the sensor's view is correct and that coverage sees the
amount of space needed to capture the desired behavior at:
n Doors
n Queues
n Points of Interest
4. Complete a risk assessment to identify any potential view obstructions in site photographs. Give
special consideration to:
n Changing ceiling heights
n Physical objects in the view of the sensor, such as columns, cash delivery tubes, large
signs or light fixtures, etc.
5. Verify that the Site Installation Specifications correctly identifies the number of sensors and that
the orientation for each sensor is correct.