5.1 Requirements to Meet EMC Directive
5.1.1 EMC directive
5 - 3
1
OVERVIEW
2
SYSTEM
CONFIGURATION
3
SPECIFICATIONS
4
PART NAME AND
SETTINGS
5
EMC AND LOW
VOLTAGE
DIRECTIVE
6
INSTALLATION
7
WIRING
8
OPTION
*1: The GOT is an open type device (device installed to another device) and must be installed in a conductive control
panel.
The above test items are conducted in the condition where the GOT is installed on the conductive control panel
and combined with the Mitsubishi PLC.
*2: QP: Quasi-peak value, Mean : Average value
*3: The above test items are conducted in the following conditions.
30M-230MHz QP: 40dB V/m (10m in measurement range)
230M-1000MHz QP: 47dB V/m (10m in measurement range)
Applied
standard
Test standard Test details Standard value
EN61131-2
: 2007
EN61000-4-8
Power supply frequency
magnetic field immunity
Test for checking normal operations
under the circumstance exposed to
the ferromagnetic field noise of the
power supply frequency (50/60Hz).
30 A/m
EN61000-4-11
Instantaneous power
failure and voltage dips
immunity
Test for checking normal operations
at instantaneous power failure.
AC power type
0.5 cycle 0% (interval 1 to 10s)
250/300 cycle 0%
10/12 cycle 40%
25/30 cycle 70%
DC power type
10ms (interval 1 to 10s)