► After this, and before the countdown ends, close the water supply again.
The message "Separate from mains" appears after the countdown ends.
► Disconnect the machine from the power supply by pulling the power plug.
The water system was "flooded" to cool it.
All boilers are filled.
The water system of the machine is depressurised.
Option 2: Cancelling water drainage
► Select the [Cancel] field.
This takes you back to the "Test / calibration" menu.
Option 3: Filling the machine with water
► Connect the water supply to the machine and open the water tap.
► Connect the machine power plug to the power supply.
The machine is started up.
The "Pre start services" menu appears automatically.
► Select the [Start fill up] field.
The "Safety switch" prompt appears.
► Select the [OK] or [No] field, according to the machine equipment.
When a "drained", in other words "flooded", machine is connected to the power supply again
and switched on, the menu for filling the machine appears automatically. A description of how
to fill the machine is provided below.
The "Start leakage test" is a commissioning parameter that is only used during assembly at
the factory.
See "System" - "System Parameters" - "02 Safety switch" for further information on the "Safety
switch" equipment.