3. Fitting the Terminal Housing to the motor
1. Remove the existing motor Terminal Housing (the Terminal
Housing will become the motor Terminal Housing).
2. Align the Terminal Housing with the motor Terminal Housing.
3. Secure the Terminal Housing to the motor Terminal Housing.
Notes:
• Ensure that the Terminal Housing is tted to the motor with
the Power Module heatsink over the non-drive end of the
motor.
• There are three dierent Terminal Housings, please ensure
you have the correct Terminal Housing conguration for the
motor to which it is to be tted.
• All the required xing bolts are supplied in the packaging
with the product.
• On the FS80/90 Terminal Housings there are two additional
xing points which are the earthing points between the Ter‐
minal Housing and the motor. These earthing points must be
used and therefore, the earthing cable does not need to be
tted.
• The FS80/90 Terminal Housings cannot be tted directly over
the terminal block of the motor - the terminal block of the
motor must be removed from the motor, then the Terminal
Housing is tted to the motor and then the motor terminal
block is tted back onto the motor.
• Exact dimensions and xing points of the Terminal Housing:
Mechanical Installation (Page 38).
• The tightening torques for tting the Terminal Housing to the
motor terminal box are contained in the Operating Instruc‐
tions for the motor:
LA/LE motors for mounting on SIMOGEAR gearboxes
(http://support.automation.siemens.com/WW/view/en/
60666508).
• If the SINAMICS G110M is ordered as a complete system,
then all mechanical and electrical installation is completed in
the factory prior to delivery.
Installation
4.2 System Installation
Distributed converter for SIMOGEAR geared motors