10 Checklist, Part 2 of 2
We recommend that you print out and work through the checklist for commissioning, replacing the
measuring system and when changing the parameterization of a previously accepted system and
store it as part of the overall system documentation.
This User Manual was read and
understood
Document no.:
TR-ECE-BA-GB-0139
Verify that the measuring system
can be used for the present
automation task based on the
specified safety requirements
● Safety functions of the fail-safe
processing unit
● Compliance with all technical
data
● Chapter
Safety functions of the fail-
safe processing unit,
Page 16
● Product data sheets
www.tr-
electronic.com/s/S021065
● The power supply unit used
must meet the requirements of
● Chapter Supply voltage,
Page 19
Proper
PROFINET installation
● Compliance with the valid
international standards or
PROFIBUS User Organization
guidelines specified for
PROFINET / PROFIsafe
● Chapter
Installation / Preparation for
Commissioning,
from Page 17
● Chapter
Commissioning, Page 27
After commissioning and
parameter changes
– System test
– Validation
(Settings – Axis)
● During commissioning and
whenever parameters have been
changed
– all relevant safety functions
involved must be checked
– if several (similar) axes are
used, make sure that the
settings have been made for the
desired axis
● Chapter
PROFIsafe destination
address “F_Dest_Add,
Page 20
● Chapter
Address assignment, Page 29
● Chapter
PNO profile parameteriza-
tion, from page 76
● Chapter
Preset adjustment function
(PNO profile), Page 87
● Chapter
Parameterization TR-profile,
from Page 101
● Chapter
Preset adjustment function
(TR profile), Page 118
● Chapter
Legacy-profile
parameterization,
from Page 125.
● Chapter
Preset adjustment function
(legacy profile), Page 130
Continued on next page