HP10E / HP12E / HP15E / HP20E - Dairy design 3. Installation and commissioning
3-1© VEMAG 2013
3. Installation and commissioning
3.1 Transporting the machine
The machine may only be transported using suitable lifting trucks or fork-
lift trucks with a capacity of at least 1,500 kg. If at all possible, move the
fork-lift/lifting truck under the machine from the outlet side.
Danger!
Never tilt the machine when transporting it and when setting it up, always
keep it horizontal. This prevents the machine tipping over. When trans-
porting the machine, it is essential to observe its centre of gravity.
Fig. 3-1
Centre of gravity of the
machine
270
538
Fig. 3-2
Centre of gravity of the
machine
261