6-20
Cisco CRS-1 Series Carrier Routing System Getting Started Guide
Chapter 6 Managing Cisco IOS XR Software Packages
Package Management Procedures
Tip Use the test option to preview the effects of a command without impacting the running system.
Activation and Deactivation Prerequisites
The following prerequisites must be met for a package to be activated or deactivated.
Initial activation of any package must always be performed for the default set of supported card
types.
If a ROM monitor upgrade is required for the software package, the upgrade must be completed
before the package is activated. For ROM monitor upgrade information and procedures, refer to
Appendix B, “Upgrading and Downgrading ROM Monitor Software.”
Although more than one version of a software package can be added to a storage device, only one
version of a package can be active for any card.
The package must be compatible with the card for which it is being activated.
Some packages require the activation or deactivation of other packages.
The package being activated must be compatible with the current active software set.
While a software package is being activated, other requests are not allowed to execute on the system.
Each installation request is assigned a requestID, which can be used later to review the events.
Package activation is complete when the following message is displayed:
Install 1: Activation operation successful.
Activation is performed only after the package compatibility checks have passed. If a conflict is found,
an on-screen error message is displayed.
Package Management Procedures
Review the concepts in the “Information About Package Management” section on page 6-17 before
performing the following tasks. The following sections describe package management tasks:
Displaying the Active Packages for All Cards, page 6-21
Displaying the Active Packages for a Single Card, page 6-22
Copying, Adding, and Activating Packages, page 6-22
Rolling Back to Committed Software, page 6-27
Committing the Active Software Change, page 6-28
Removing Inactive Packages from the Router, page 6-29

Table of Contents

Other manuals for Cisco CRS-1 - Carrier Routing System Router

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Cisco CRS-1 - Carrier Routing System Router and is the answer not in the manual?

Cisco CRS-1 - Carrier Routing System Router Specifications

General IconGeneral
BrandCisco
ModelCRS-1 - Carrier Routing System Router
CategoryNetwork Router
LanguageEnglish

Related product manuals