Scenario PRE A004 - Pre-Delivery Check
Page no. 369 Chapter 5
SC-PRE-A004.fm
Scenario PRE A004 - Pre-Delivery Check Chapter 5
1CONTEXT
This scenario provides a check list for use in planning and carrying out a pre-delivery check visit.
2STEERING GUIDE
# Requirement Reference Who? Done?
Storage conditions
1 Check preparation of pre-installation
storage room
Chapter 4 Pre-Installation
System Requirements, sec-
tion 9 Planning for Storage
Hospital engi-
neer
Room preparation
2 Check the proposed layout and prepa-
rations for cable runs.
Chapter 4 Pre-Installation
System Requirements, sec-
tion 10 Room Layout Plan-
ning
Site planner
3 Check floor and anchorage preparation. Chapter 4 Pre-Installation
System Requirements, sec-
tion 10 Room Layout Plan-
ning
Flooring special-
ist
4 Check access requirements. Chapter 4 Pre-Installation
System Requirements, sec-
tion 4 Structural Require-
ments
Hospital engi-
neer
Radiation protection (wall, ceiling, floor, doors)
5 Check preparation for radiation protec-
tion (wall, ceiling, doors);
Chapter 4 Pre-Installation
System Requirements, sec-
tion 8 Planning for Radiation
Protection
Radiation protec-
tion specialist
Insite connection
6 Check preparations for Insite broad-
band connection
Chapter 4 Pre-Installation
System Requirements, sec-
tion 11 Insite Connection
Hospital Net-
work Administra-
tor
Lighting
7 Check room lighting conditions Chapter 4 Pre-Installation
System Requirements, sec-
tion 7 Room Lighting
Lighting special-
ist