MX10016 Site Preparation Overview
IN THIS SECTION
Site Preparation Checklist | 89
Environmental Requirements and Specifications | 90
General Site Guidelines | 91
Site Electrical Wiring Guidelines | 92
MX10016 Rack Requirements | 93
Clearance Requirements for Airflow and Hardware Maintenance for an MX10016 | 95
Site Preparation Checklist
The checklist in Table 27 on page 89 summarizes the tasks you need to perform when preparing a site for
an MX10016 installation.
Table 27: Site Preparation Checklist
DatePerformed ByFor More InformationItem or Task
Environment
“Environmental Requirements
and Specifications” on page 90
Verify that environmental factors such as
temperature and humidity do not exceed
router tolerances.
Power
Measure the distance between external
power sources and the router installation site.
“MX10016 Power Planning” on
page 96
Calculate the power consumption and
requirements.
Rack
“MX10016 Rack Requirements”
on page 93
Verify that your rack meets the minimum
requirements for the installing the router.
89